Outage History
Highway 17 East Outage for Conductor Replacements (67) – New
Planned Outage
Customers Affected: | 65 |
Crew Status: | Preparation |
Cause: | Conductor replacement |
Outage Start: | 8:30, October 30, 2024 |
Restoration Time: | 12:30, October 30, 2024 |
Notes: | There will be a planned outage on October 30 from 8:30am to 12:30pm to replace conductors in the Highway 17 area around Dugas Bay, from west of Bayview Drive easterly to the city limits. The area will include all Bayview Drive, Ross Drive, Birchcove Road and other minor roads. |
Power Outage on Main Street West (66) – Restored
This outage has been restored.
Power Outage on Main Street West (66) – Updated
General Outage
Customers Affected: | 240 |
Crew Status: | Fixed |
Cause: | unknown |
Outage Start: | 9:30 |
Restoration Time: | 12:33 |
Notes: |
North Bay Hydro |
Power Outage on Main Street West (66) – New
General Outage
Customers Affected: | 240 |
Crew Status: | Investigating |
Cause: | unknown |
Outage Start: | 9:30 |
Restoration Time: | 15:30 |
Notes: |
North Bay Hydro |
Planned Outage – Hwy 17 East Area (65) – Restored
This outage has been restored.
Planned Outage – Hwy 17 East Area (65) – New
Planned Outage
Customers Affected: | 50 |
Crew Status: | Planned |
Cause: | Equipment Replacement |
Outage Start: | 6:00 |
Restoration Time: | 9:00 |
Notes: | Outage Notice: North Bay Hydro will be performing a planned outage affecting approximately 50 customers in the area surrounding Highway 17 East including Bayfield Rd and Birchcove Rd in order to safely replace equipment. The outage is scheduled to take place on Sunday, September 15, 2024 @ 6:00am and may be up to 3 hours in duration. |
Power Outage on Cartier St. (64) – Restored
This outage has been restored.
Power Outage on Cartier St. (64) – Updated
General Outage
Customers Affected: | 20 |
Crew Status: | Restored |
Cause: | Under ground Cable Fault & blown transformer |
Outage Start: | 15:20 |
Restoration Time: | 21:30 |
Notes: |
North Bay Hydro |
Power Outage on Cartier St. (64) – New
General Outage
Customers Affected: | 20 |
Crew Status: | Repairing |
Cause: | Under ground Cable Fault & blown transformer |
Outage Start: | 15:20 |
Restoration Time: | 22:00 |
Notes: |
North Bay Hydro |
Outage – Areas Surrounding Hwy 17 East & Progress Rd (63) – Restored
This outage has been restored.