Outage History

Outage – West Ferris (50) – New

General Outage

Customers Affected: 950
Crew Status: Investigating
Cause: Unknown
Outage Start: 13:18
Restoration Time: 16:00
Notes: North Bay Hydro is aware of an outage affecting approximately 950 customers in West Ferris in the area surrounding Charles St. The cause of the outage is currently unknown, crews are investigating. Estimated restoration time 4:00pm.

Planned Outage – Monday, May 13, 2024 (49) – New

Planned Outage

Customers Affected: 43
Crew Status: In Progress
Cause: Equipment Replacement
Outage Start: 9:00
Restoration Time: 13:00
Notes: Planned outage affecting 43 customers in order for crews to safely replace line equipment.

Outage – Regal Rd (46) – Updated

General Outage

Customers Affected: 40
Crew Status: Investigating
Cause: TBD
Outage Start: 11:47
Restoration Time: 13:40
Notes: Update: North Bay Hydro has restored approximately 120 customers in the affected area, however approximately 40 customers on Regal Rd and Peninsula Rd remain out. Power was restored at 1:40pm.

Outage – Regal Rd (46) – New

General Outage

Customers Affected: 40
Crew Status: Investigating
Cause: TBD
Outage Start: 11:47
Restoration Time: 14:00
Notes: Update: North Bay Hydro has restored approximately 120 customers in the affected area, however approximately 40 customers on Regal Rd and Peninsula Rd remain out. Estimated restoration time is 2:00pm.

Outage – Areas Surrounding Highway 63 & Peninsula Rd (45) – Updated

General Outage

Customers Affected: 750
Crew Status: Restoration Complete
Cause: Loss of Supply
Outage Start: 10:07
Restoration Time: 10:27
Notes: Update: Power has been restored to the affected areas, if your power is still out, please contact North Bay Hydro.