West Ferris Outage (22) – Updated

General Outage

Customers Affected: 690
Crew Status: On-site
Cause: Broken Pole
Outage Start: 10:14
Restoration Time: 10:50
Notes: Power was restored at 10:50am.

West Ferris Outage (22) – New

General Outage

Customers Affected: 690
Crew Status: On-site
Cause: Investigating
Outage Start: 10:14
Restoration Time: 14:00
Notes: There is a power outage in the West Ferris area on Campbell Ave, Charles St., Whitney Ave, Nelson St, MacDonald Ave and Ethel St.  Crews are currently investigating.  Restoration time estimated at 2:00pm until further information becomes available.

Commerce Cres – Scheduled Outage (21) – New

Planned Outage

Customers Affected: 10
Crew Status: Scheduled
Cause: Scheduled Line Work
Outage Start: September 7, 2021 @ 18:00
Restoration Time: September 7, 2021 @ 20:00
Notes: North Bay Hydro must perform an outage on Commerce Cres to safely remove high voltage conductors and equipment. The outage is scheduled to take place on Tuesday, September 7, 2021 @ 6:00 pm and will be approximately 2 hours in duration.  

West Ferris Outage (20) – Updated

General Outage

Customers Affected: 1200
Crew Status: Investigating
Cause: Unknown
Outage Start: 8:41
Restoration Time: 9:29
Notes: North Bay Hydro has restored power to the affected areas in the West Ferris area

West Ferris Outage (20) – New

General Outage

Customers Affected: 1200
Crew Status: Investigating
Cause: Unknown
Outage Start: 8:41
Restoration Time: 10:00
Notes: North bay Hydro is aware of an outage affecting approximately 1200 customers in the West Ferris area. The cause of the outage is currently unknown, crews are investigating. Estimated restoration time is 10:00 

Outage – Front Ave, Third Ave, Fifth Ave Areas (19) – New

General Outage

Customers Affected: 50
Crew Status: Planned Repairs
Cause: Damaged Equipment
Outage Start: 10:00
Restoration Time: 11:00
Notes: North Bay Hydro must perform an emergency outage for equipment repairs affecting approximately 50 customers in the areas surrounding Front St, Third Ave W, & Fifth Ave W. The outage will start approximately at 10:00 am and will be approximately 1 hour in duration.