Outage History

Hwy 63 Outage (2) – New

General Outage

Customers Affected: 160
Crew Status: Repairs in Progress
Cause: Broken Conductor
Outage Start: 1:35
Restoration Time: 6:00
Notes: Update: North Bay Hydro is aware of an outage in the Hwy 63 Area affecting approximately 160 customers. The cause of the outage is due to a broken conductor, repairs are in progress.  Estimated restoration time is 6:00 am.

Hwy 63 Outage (1) – Updated

General Outage

Customers Affected: 160
Crew Status: Investigating
Cause: Unknown
Outage Start: 1:35
Restoration Time: 6:00
Notes: Update: North Bay Hydro is aware of an outage in the Hwy 63 Area affecting approximately 160 customers. The cause of the outage is due to a broken conductor, repairs are in progress.  Estimated restoration time is 6:00 am.

Hwy 63 Outage (1) – New

General Outage

Customers Affected: 160
Crew Status: Investigating
Cause: Unknown
Outage Start: 1:35
Restoration Time: 6:00
Notes: North Bay Hydro is aware of an outage in the Hwy 63 Area affecting approximately 160 customers. The cause of the outage is currently unknown and crews are investigating. Estimated restoration time is 6:00 am.

Hwy 63 Area Outage (8) – Updated

General Outage

Customers Affected: 20
Crew Status: Repairs are in progress
Cause: Broken Insulator
Outage Start: 00:00
Restoration Time: 05:00
Notes: Update: All areas affected by the Hwy 63 outage have been restored. If your power is still out, please contact North Bay Hydro

Hwy 63 Area Outage (8) – New

General Outage

Customers Affected: 20
Crew Status: Repairs are in progress
Cause: Broken Insulator
Outage Start: 00:00
Restoration Time: 05:30
Notes: Update: North Bay Hydro is aware of an outage in the Hwy 63 area still affecting approximately 20 customers. The cause of the outage is from a broken insulator, repairs are in progress. Estimated restoration time is 5:30 am

Hwy 63 Outage (7) – New

General Outage

Customers Affected: 230
Crew Status: Investigating
Cause: Unknown
Outage Start: 00:00
Restoration Time: 04:00
Notes: North Bay Hydro is aware of an outage in the Hwy 63, Anita Ave, and Feronia Rd area affecting approximately 230 customers. The cause of the outage is currently unknown. Crews are investigating. Estimated restoration time is 4:00 am

Gormanville Rd, Larocque Rd, Pinewood Area (6) – Updated

General Outage

Customers Affected: 520
Crew Status: Investigating
Cause: Unknown
Outage Start: 13:50
Restoration Time: 16:30
Notes: Update: Approximately 400 customers have been restored in the Gormanville Rd and Pinewood area. Approximately 120 customers remain out of power in the Larocque Rd & Cedar Heights Rd area. The cause of the outage is currently unknown. Estimated restoration time is 4:30 pm