Ski Club Rd – Planned Outage (2) – New

Planned Outage

Customers Affected: 40
Crew Status: In Progress
Cause: Insfrastructure Upgrades
Outage Start: March 2, 2020 @ 9:00
Restoration Time: March 2, 2020 @ 13:00
Notes: North Bay Hydro must perform a necessary planned outage for infrastructure upgrades. Outage will be approximately 4 hours in duration on Monday, March 2, 2020, from 9:00 am to 1:00 pm.

West Ferris (2) – Updated

General Outage

Customers Affected: 900
Crew Status: Investigating
Cause: Station Equipment Failure
Outage Start: 15:20
Restoration Time: 16:15
Notes: The power has been restored in the Lakeshore Drive/Nipissing Junction area as of 4:15 pm.  The cause was due substation equipment failure.  If your power is still out please call North Bay Hydro.

West Ferris (2) – New

General Outage

Customers Affected: 900
Crew Status: Investigating
Cause: Unknown
Outage Start: 15:20
Restoration Time: 17:00
Notes: There is an outage in the Lakeshore Drive/Nipissing Junction area.  The cause is unknown and crews are investigating.  Approximately 900 customers are affected.  Restoration time is estimated to be 5 pm.

Jane/Main W/Pinewood Area (2) – Updated

General Outage

Customers Affected: 1050
Crew Status: On scene
Cause: Broken Conductor in Substation
Outage Start: 7:17
Restoration Time: 9:05
Notes: The power has been restored in all areas as of 9:05 am.  If your power is still out, please contact North Bay Hydro.

Jane/Main W/Pinewood Area (2) – New

General Outage

Customers Affected: 1050
Crew Status: On scene
Cause: Broken Conductor in Substation
Outage Start: 7:17
Restoration Time: 9:00
Notes: There is a power outage due to a broken conductor in substation #19.  Crews are working to re-route power from other substations.  Approximately 1050 customers are affected.  Estimated restoration time is 9 am.

Outage 2 – April 7, 2017 (23) – Updated

General Outage

Customers Affected: 1300
Crew Status: Making repairs/removing tree
Cause: Downed Tree on HWY 63 at Anita
Outage Start: 8:05am
Restoration Time: 8:35am