• Left Homepage Side Bar

    North Bay Hydro’s Regulatory Scorecard

    The Ontario Energy Board (OEB) has developed a scorecard for all local distribution companies across the Province as a tool to allow customers to gain a better sense of how well their utility is performing over a 5 year period. Utility scorecards track and show comprehensive performance information for each electricity utility in Ontario, over a range of time and for a specific year.

    Click Here



    Residential Customer

    Rights and

    Responsibilities

    Disconnection

    Click Here


    Emailing North Bay Hydro?

    Due to high volumes of SPAM email, some emails will occasionally be blocked or bounced.

    If you get a bounce, or do not receive a response please contact 705-474-8100 Opt 2 to resolve the issue.

Highway 63 Area (1) – New

Posted on November 16th, 2020 at 3:58 am

General Outage

Customers Affected: 80
Crew Status: Restoring
Cause: Tree fell on line and broke conductors
Outage Start: 1:28am
Restoration Time: 6:00am
Notes: There is an outage on Highway 63, including Silver Lady Lane and part of Anita Avenue, due to a tree that fell on a line and broke the conductors.  The crews are currently on site removing the tree and reconnecting the conductors.  Restoration time expected at 6:00am.

Airport Hill Outage (1) – Restored

Posted on September 18th, 2020 at 5:02 am

This outage has been restored.

Airport Hill Outage (2) – Restored

Posted on September 18th, 2020 at 5:02 am

This outage has been restored.

Airport Hill Outage (3) – Restored

Posted on September 18th, 2020 at 5:02 am

This outage has been restored.

Airport Hill Outage (4) – Restored

Posted on September 18th, 2020 at 5:01 am

This outage has been restored.

Airport Hill Outage (5) – Restored

Posted on September 18th, 2020 at 5:01 am

This outage has been restored.

Airport Hill Outage (6) – Restored

Posted on September 18th, 2020 at 5:01 am

This outage has been restored.

Downtown Area Outage (1) – Restored

Posted on September 14th, 2020 at 1:32 am

This outage has been restored.

Downtown Area Outage (1) – Updated

Posted on September 14th, 2020 at 1:32 am

General Outage

Customers Affected: 2241
Crew Status: Restoring
Cause: Faulty switch
Outage Start: 11:10
Restoration Time: 4:00am
Notes: Outage due to a faulty switch.  Crews are on site to isolate and restore power.  Power expected to be restored by 4:00am.  Outage partially restored at 1:32am.

Downtown Area Outage (1) – Updated

Posted on September 14th, 2020 at 1:30 am

General Outage

Customers Affected: 2241
Crew Status: Restoring
Cause: Faulty switch
Outage Start: 11:10
Restoration Time: 4:00am
Notes: Outage due to a faulty switch.  Crews are on site to isolate and restore power.  Power expected to be restored by 4:00am.  Outage partially restored at 1:32am.
«       1    2    3    4    5    6    7    8    9    10    11    12    13    14    15    16    17    18    19    20    21    22    23    24    25    26    27    28    29    30    31    32    33    34    35    36    37    38    39       »