• Left Homepage Side Bar

    North Bay Hydro’s Regulatory Scorecard

    The Ontario Energy Board (OEB) has developed a scorecard for all local distribution companies across the Province as a tool to allow customers to gain a better sense of how well their utility is performing over a 5 year period. Utility scorecards track and show comprehensive performance information for each electricity utility in Ontario, over a range of time and for a specific year.

    Click Here



    Residential Customer

    Rights and

    Responsibilities

    Disconnection

    Click Here


    Emailing North Bay Hydro?

    Due to high volumes of SPAM email, some emails will occasionally be blocked or bounced.

    If you get a bounce, or do not receive a response please contact 705-474-8100 Opt 2 to resolve the issue.

Outage – Pinewood Park Dr, Birches Rd, Decaire Rd Area (7) – New

Posted on July 8th, 2021 at 2:10 pm

General Outage

Customers Affected: 300
Crew Status: Investigating
Cause: Unknown
Outage Start: 13:52
Restoration Time: 17:00
Notes: North Bay Hydro is aware of an outage affecting approximately 300 customers in the south side of the city in the areas surrounding Pinewood Park Dr, Birches Rd, and Decaire Rd. The cause of the outage is currently unknown, crews are investigating. Estimated restoration time is 5:00 pm 

Outage – Airport Rd & Carmichael Dr Area (5) – Restored

Posted on April 30th, 2021 at 5:33 pm

This outage has been restored.

Outage – Airport Rd & Carmichael Dr Area (6) – Restored

Posted on April 30th, 2021 at 5:33 pm

This outage has been restored.

Peninsula Road (4) – Restored

Posted on April 10th, 2021 at 2:01 pm

This outage has been restored.

Peninsula Road (4) – Updated

Posted on April 10th, 2021 at 2:01 pm

General Outage

Customers Affected: 60
Crew Status: Restored
Cause: Tree broke conductors
Outage Start: 12:00
Restoration Time: 15:30
Notes: A tree fell on a line and broke 2 conductors in the Peninsula and North Shore Area.  Power was restored at 13:45.

Peninsula Road (4) – New

Posted on April 10th, 2021 at 1:41 pm

General Outage

Customers Affected: 60
Crew Status: Restoring
Cause: Tree broke conductors
Outage Start: 12:00
Restoration Time: 15:30
Notes: A tree fell on a line and broke 2 conductors in the Peninsula and North Shore Area.  Crews are currently on-site and restoring power.  Approximate restoration time is 15:30.

Tree Contact Outage (3) – Restored

Posted on March 30th, 2021 at 4:18 pm

This outage has been restored.

Tree Contact Outage (3) – Updated

Posted on March 30th, 2021 at 4:18 pm

General Outage

Customers Affected: 150
Crew Status: Repairs in Progress
Cause: Tree Contact
Outage Start: 16:00
Restoration Time: 16:15
Notes: Update: Power has been restored to the areas of Four Mile Lake Rd, Chadbourne Dr, and Widdifield Stn Rd. If your power is still out, please contact North Bay Hydro.

Tree Contact Outage (3) – New

Posted on March 30th, 2021 at 4:10 pm

General Outage

Customers Affected: 150
Crew Status: Repairs in Progress
Cause: Tree Contact
Outage Start: 16:00
Restoration Time: 17:00
Notes: North Bay Hydro is aware of an outage affecting 150 customers in the areas of Four Mile Lake Rd, Chadbourne Dr, and Widdifield Stn Rd. The cause of the outage is due to a tree contact with the line. Repairs are in progress. Estimated restoration time is 5:00pm.

Shorewood Road Outage (2) – Restored

Posted on March 29th, 2021 at 8:35 am

This outage has been restored.

«       1    2    3    4    5    6    7    8    9    10    11    12    13    14    15    16    17    18    19    20    21    22    23    24    25    26    27    28    29    30    31    32    33    34    35    36    37    38    39    40    41    42    43    44       »