    The Ontario Energy Board (OEB) has developed a scorecard for all local distribution companies across the Province as a tool to allow customers to gain a better sense of how well their utility is performing over a 5 year period. Utility scorecards track and show comprehensive performance information for each electricity utility in Ontario, over a range of time and for a specific year.

    Click Here


    2024 IRM Application

    Download Application


    Residential Customer

    Rights and

    Responsibilities:

    Disconnections

    Click Here


Outage 1 – April 6, 2016 (1) – Updated

Posted on April 6th, 2016 at 7:09 pm

General Outage

Customers Affected: 80
Crew Status: Isolated issue, repairing issue
Cause: broken pole
Outage Start: 4:21pm April 6, 2016
Restoration Time: 7:30pm April 6, 2015
Notes: Outage fully restored as of 6:59pm.

Outage 1 – April 6, 2016 (1) – Updated

Posted on April 6th, 2016 at 5:35 pm

General Outage

Customers Affected: 80
Crew Status: Isolated issue, repairing issue
Cause: broken pole
Outage Start: 4:21pm April 6, 2016
Restoration Time: 7:30pm April 6, 2015
Notes: Issue found and isolated returning power to 300 customers as of 5:12pm.  Crews working to restore power to remaining 80 customers by repairing broken pole.

Outage 1 – April 6, 2016 (1) – New

Posted on April 6th, 2016 at 4:53 pm

General Outage

Customers Affected: 380
Crew Status: Investigating
Cause: Unknown
Outage Start: 4:21pm April 6, 2016
Restoration Time: Unknown at this time
Notes: Crews patrolling area to find cause.  

March 21, 2016 – Outage 1 (1) – Restored

Posted on March 21st, 2016 at 1:01 pm

This outage has been restored.

March 21, 2016 – Outage 1 (1) – Updated

Posted on March 21st, 2016 at 1:00 pm

General Outage

Customers Affected: 1050
Crew Status: Working to restore power
Cause: Squirrel Contact at Station
Outage Start: 11:18am
Restoration Time: 1pm
Notes: Power fully restored as of 12:56pm.

March 21, 2016 – Outage 1 (1) – Updated

Posted on March 21st, 2016 at 12:47 pm

General Outage

Customers Affected: 1050
Crew Status: Working to restore power
Cause: Squirrel Contact at Station
Outage Start: 11:18am
Restoration Time: 1pm
Notes: Partial restoration at 12:20 and 12:35pm.  Appox. 250 customers still without power.  1pm is still the estimated time for full restoration

March 21, 2016 – Outage 1 (1) – Updated

Posted on March 21st, 2016 at 12:08 pm

General Outage

Customers Affected: 1050
Crew Status: Working to restore power
Cause: Squirrel Contact at Station
Outage Start: 11:18am
Restoration Time: 1pm
Notes: Crews have found problem, squirrel contact at the MS19 station. Crews switching now.

March 21, 2016 – Outage 1 (1) – Updated

Posted on March 21st, 2016 at 12:07 pm

General Outage

Customers Affected: 1050
Crew Status: Working to restore power
Cause: Squirrel Contact at Station
Outage Start: 11:18am
Restoration Time: 1pm
Notes: Crews have found problem, squirrel contact at the MS19 station. Crews working on switching to restore power to affected customers.  Restoration time will be updated shortly.

March 21, 2016 – Outage 1 (1) – New

Posted on March 21st, 2016 at 11:40 am

General Outage

Customers Affected: 1050
Crew Status: Working to restore power
Cause: Squirrel Contact at Station
Outage Start: 11:18am
Restoration Time: unknown at this time
Notes: Crews have found problem, squirrel contact at the MS19 station. Crews working on switching to restore power to affected customers.  Restoration time will be updated shortly.

March 10, 2016 – Power Outage 1 (1) – Restored

Posted on March 10th, 2016 at 2:49 pm

This outage has been restored.

«       1    2    3    4    5    6    7    8    9    10    11    12    13    14    15    16    17    18    19    20    21    22    23    24    25    26    27    28    29    30    31    32    33    34    35    36    37    38    39    40    41    42    43    44    45    46    47    48    49    50       »